FCC Construction delivered site improvements for the City of Ionia’s Steele Park in Ionia, Michigan, transforming a former strip mall and gas station site into a public park with a pavilion, restrooms, sport courts, and pedestrian pathways. Built within a 100-year floodplain, the seven-month, hard-bid project finished with zero lost-time incidents.

Open-air pavilion at Steele Park in Ionia, MI, with a wood plank ceiling and the City of Ionia emblem above the stage wall.

A new public park starts below the surface. At Steele Park in Ionia, Michigan, the ground itself set the pace for everything built on top of it. FCC Construction partnered with the City of Ionia on improvements to Steele Park, transforming a site once home to a strip mall and gas station into a new public park. The community now has a place to recreate and gather on ground that had sat empty for years.

City of Ionia Steele Park sign beside a new sidewalk and parking lot, with the park pavilion in the background.

FCC Construction, Inc.

From Vacant Lot to Community Park

The improvements covered 8.17 acres of disturbance and added amenities for everyday use and community events:

  • A new parking lot

  • Restrooms

  • A pavilion for music and events

  • Pickleball and volleyball courts

  • Pedestrian pathways

The project was funded through DNR Trust Fund grants, a MEDC grant, private donations, and local park improvement tax dollars. FCC delivered the work through a hard-bid approach alongside architect MCSA and the engineering team of LRE Engineers & Surveyors, Classic Engineering, Soils & Structures, and Matrix Engineering.

Building Up Out of the Floodplain

The site sits within a 100-year floodplain, and its soils were unsuitable for construction as they stood. The team removed 633 cubic yards of unsuitable soil and brought in four to five feet of fill to raise the construction area above the floodplain.

The property's earlier life left its own surprises. Crews uncovered a number of undocumented structures on site during the work. FCC Excavating handled those unexpected conditions in the field so the rest of the project could move forward on solid ground.

Communicating Through a Weather Delay

Rising water on the floodplain delayed the project by two weeks. FCC notified the City and documented the delay in the schedule. From there, the team worked with subcontractors to make up the time.

That response grew out of a steady communication rhythm. Bi-weekly owner and architect meetings and site walks kept the City and design team aligned throughout construction. Updated schedules and three-week look-aheads went out at least every two weeks, so the City always had a current view of where the project stood.

New pickleball courts at Steele Park in Ionia, MI, surrounded by black chain-link fencing, with park buildings beyond.

FCC Construction, Inc.

Quality and Safety Through Closeout

FCC coordinated 31 subcontractors and suppliers on Steele Park with zero lost-time incidents. The park was delivered with no failed inspections and only a minimal punch list, on schedule and within budget, over a seven-month duration.

Steele Park also marked Jake Kopenski's first project leading as superintendent. Jake led the field effort alongside the many trade partners on site, carrying the project from a vacant lot to a finished park.

What This Project Demonstrates

Public projects carry a particular kind of accountability. The funding comes from many sources, including local taxpayers, and the community watches every stage take shape. Steele Park shows how FCC approaches complex site work: with the same communication and care we bring to any building project. The owner hears about changes from us first and sees them reflected in the schedule.

Planning a municipal project or a site with challenging ground conditions? We'd welcome the conversation.